Long trench jobs are won or lost on the hire bill. Keep four panel sets on hire when the trench only needs two and the margin goes to the yard; send them back too early and the crew stands around. The Bennett Park crew managed it by calling as the job changed, and we changed the gear.
The three configurations
- From 31 March: four lower steel shoring panels (5000 x 2410 mm) and four upper panels (5000 x 2010 mm) plus a spare upper, 3000 mm and 2000 mm handrails (four of each), a davit arm and recovery winch kit, and a ladder access unit. Delivery and pick-up included, Sydney metro.
- From 28 April: scaled down to two lower and two upper panels (plus the spare) as the open length shortened.
- From 2 August to 10 September: switched to two aluminium shoring boxes (lower 5 x 2.4 m and upper 5 x 1.7 m, each with a 1493 strut), a ladder access platform, a 3.8 to 6.6 m extension ladder and a 4 m lifting chain, delivery and pick-up included.
Each period carried its damage waiver and environmental levy as lines on the invoice. Each change was a phone call, not a new tender. The crane truck came when the gear changed and not otherwise.
Steel to aluminium
The steel panel sets suit a deep trench placed by a big excavator. When the job moved to a shorter, shallower run placed by a smaller machine, aluminium boxes with struts did the same job at a lighter rate and with less lifting. Many long jobs go the same way; the point is to have both available on one account.